Chattanooga Sports Authority Meeting - 11/12/2026

Agenda Items & Discussion

  • Financial progress report (as of October 31, 2026): City finance staff presented project-to-date and FY27 year-to-date figures. Sales tax figures are current through September 2026, and stadium depreciation of $2.4 million is shown as a note. Staff confirmed the stadium project is complete and appropriated funds have been spent; the June 30, 2026 audit will also reflect this.
  • Project closeout reports: City Engineer Bill Payne reviewed closeout reports for each contract under the $86 million budget ($80M from 2024 Series A/B bonds, $5M from Series C, and $1M in anticipated accrued interest). EMJ's construction contract grew from a $76M guaranteed maximum price to about $78.9M, largely funded from contingency. Total Sports Authority contracts came to $85,529,925.86, under the $86M budget.
  • Scope shift to the tenant: About $470,000 in unused Sports Authority funds was shifted to cover items Chattanooga Professional Baseball had initially purchased, as allowed under the lease and site preparation agreements. Staff said the team still met or exceeded its $19 million tenant-supplied investment (about $19.6M including escrow interest).
  • Public infrastructure and railroads: The $10M city-funded infrastructure (West 26th Street extension, drainage under I-24, and sanitary sewer) included one-time preliminary engineering payments of about $67,000 to Norfolk Southern and $38,000 to CSX. A board member asked about future railroad charges; staff said any future costs would be handled by the City, not the Sports Authority.
  • Resolution reports: Staff reported on use of funds under Resolution SA041 ($37,486.33 previously unallocated, directed to EPB transformer work, final EMJ items, and the tenant scope shift, leaving a $0 balance) and SA044 (contract underruns directed to the tenant scope shift).
  • Debt service question: The board asked about remaining cash and debt service. The city accounting manager said interest payments have been made, mostly from capitalized interest, and the first principal payments on the 2024A and 2024B bonds are due in about three weeks. The board asked for a projection at the next meeting of whether revenue will cover debt service.
  • Temporary construction easement (item 5C): Staff informed the board that the retaining wall drawing approval required under the easement with Foundry P1 Developer has been satisfied. No action was needed.
  • Lookouts first-season recap: Managing owner Jason Freier said the ballpark was built in 17 months and that the team covered roughly $950,000 in overruns under its cost overrun guarantee. He reported more than 336,000 fans at Lookouts games, more than 30,000 attendees at other events, and 197 events in 216 days. He said about $960,000 in sales tax has been recaptured toward Series A bonds so far, ahead of JP Morgan's projections, and that the Lookouts made a $500,000 Series B lease payment in May with a second payment delivered at the meeting. He also noted 13 completed or underway projects in the TIF district and a groundbreaking for about 300 apartments on the Foundry site the following day.
  • Public comment: No public comments were offered.

Key Decisions & Votes

  • Minutes from the September meeting: Approved by voice vote.
  • Financial progress report, closeout reports, and easement update: Presented for information only; no votes taken.
  • Adjournment: Motion to adjourn moved, seconded, and approved.