Riverwalk closure: required for utility installs; goal is to reopen in Q1 2026, weather-dependent.
Project remains on schedule despite heavy rainfall; drainage system working effectively.
π Resolutions & Change Orders
Item 5 β Architect Change Order (B23001101)
Revisions: raised field level by 10 ft (groundwater contamination concerns), powerhouse/pattern shop/3rd base adjustments, kitchen equipment revisions.
Cost: $735,906.75 (offset by $400K contingency; net delta ~$335K).
Approved (unanimous).
Item 6 β SNME Construction Materials Testing Change Order (D23001302)
Adds expanded inspections (esp. 100% weld testing vs. original 10%).
Cost: +$143,615; total contract = $327,262.
Still within budget; driven by structural engineerβs discretion.
Approved (unanimous).
Item 7 β Payment to Pipe Properties (Escrow Agreement)
$167,862 payment covering site prep carrying costs.
Funded by interest accrued on bond funds (per 2024 escrow agreement).
Clarified that accrued interest belongs to PIPE per contract, though members asked for this to be reflected in project accounting.
Approved.
Item 8 β Chattanooga Gas Agreement
Extend natural gas service across riverwalk to ballpark for food operations.
Cost: up to $80,251.
Approved.
π¬ Board & Public Discussion
Unallocated Funds: After change orders, ~$300β500K remains unallocated within $86M stadium budget (separate from contractor contingency).
Savings: Some redesigns reduced construction costs; EMJβs contingency untouched to date.
Public Comment (Sean Stallings): Asked about TIF revenue to cover bonds.
Admin confirmed: Increment already generated; first batch of ~70 parcels triggered. More properties to be added within 3 yrs of stadium opening.
Board requested regular TIF revenue vs. projection reports in future meetings.