8/14/25 Chattanooga City Sports Authority Meeting

πŸ•” Call to Order & Admin

  • 3:49 PM β€” Meeting called to order.
  • Minutes (June 12, 2025) β€” Approved.
  • Public comment invited; none offered at start.

πŸ“Š Financial & Project Updates

Finance Report β€” Paul Borland (City Accounting)

  • Budget report reformatted into stadium costs and public infrastructure costs.
  • Stadium encumbrances: $59M already committed, expected to move into actual expenses by next meeting.
  • Third bank drawdown underway: $14M, reducing US Bank balance from $76M β†’ ~$61M.
  • Overall project funds remain healthy and within budget.

Construction Update β€” Sher Allen & Andy Stone (Perimeter Properties)

  • Powerhouse, pattern shop, and third-base building renovations underway.
  • Roof work, balcony steel, and riverwalk utility work progressing.
  • Drone footage showed visible stadium progress; concourses open, interiors framed, utilities advancing.
  • Riverwalk closure: required for utility installs; goal is to reopen in Q1 2026, weather-dependent.
  • Project remains on schedule despite heavy rainfall; drainage system working effectively.

πŸ“‘ Resolutions & Change Orders

Item 5 β€” Architect Change Order (B23001101)

  • Revisions: raised field level by 10 ft (groundwater contamination concerns), powerhouse/pattern shop/3rd base adjustments, kitchen equipment revisions.
  • Cost: $735,906.75 (offset by $400K contingency; net delta ~$335K).
  • Approved (unanimous).

Item 6 β€” SNME Construction Materials Testing Change Order (D23001302)

  • Adds expanded inspections (esp. 100% weld testing vs. original 10%).
  • Cost: +$143,615; total contract = $327,262.
  • Still within budget; driven by structural engineer’s discretion.
  • Approved (unanimous).

Item 7 β€” Payment to Pipe Properties (Escrow Agreement)

  • $167,862 payment covering site prep carrying costs.
  • Funded by interest accrued on bond funds (per 2024 escrow agreement).
  • Clarified that accrued interest belongs to PIPE per contract, though members asked for this to be reflected in project accounting.
  • Approved.

Item 8 β€” Chattanooga Gas Agreement

  • Extend natural gas service across riverwalk to ballpark for food operations.
  • Cost: up to $80,251.
  • Approved.

πŸ’¬ Board & Public Discussion

  • Unallocated Funds: After change orders, ~$300–500K remains unallocated within $86M stadium budget (separate from contractor contingency).
  • Savings: Some redesigns reduced construction costs; EMJ’s contingency untouched to date.
  • Public Comment (Sean Stallings): Asked about TIF revenue to cover bonds.
    • Admin confirmed: Increment already generated; first batch of ~70 parcels triggered. More properties to be added within 3 yrs of stadium opening.
    • Board requested regular TIF revenue vs. projection reports in future meetings.

‍